Electrical and BMS work in a live building: how it is planned

How electrical and BMS installation is carried out in occupied offices, hospitals and hotels: permits, isolations, out-of-hours working and handing areas back.

  • By R Z Electrical & Controls
  • Published
  • 3 min read

A live building is one that stays in use while the work goes on: an office with tenants at their desks, a hospital with patients on the wards, a hotel with guests in the rooms. Much refurbishment and fit-out work is done this way, and it changes how an electrical or BMS installation has to be planned.

The work itself is the same as on an empty site. The difference is everything around it: when it can happen, what can be switched off, and what has to be working again by morning.

Start with what has to keep running

The first question is not what is being installed but what cannot stop. In an office that may be the cooling to a server room. In a hospital it is far more: ventilation, heating and hot water, and the plant behind them. Early meetings with the people who run the building establish which systems can be interrupted, for how long, and who has to agree.

Method statements and permits

Risk assessments and method statements, often shortened to RAMS, are agreed before anyone is on site. In a live building they describe not only how the work will be done safely, but how the building and the people in it will be protected while it happens.

Larger sites also run a permit-to-work system, where each task is authorised for a set place and time. It means the building's managers always know who is working where.

Switching off safely

Electrical equipment is made dead before it is worked on wherever that is possible. Each isolation is planned and agreed in advance, the circuit is proved dead before work starts, and it is tested again before it is handed back.

Out-of-hours and weekend working

Where work would disturb the people in the building, it moves to evenings, nights or weekends. That needs more planning, not less. Materials have to be on site beforehand, access and security arranged, and every shift has to end with the area safe and usable.

Taking out and putting back

Sometimes existing wiring has to come out of the way so that new equipment can go in, and then be put back. Checking it afterwards matters as much as the work itself: it shows that what was reconnected works as it did before.

Hospitals and other critical sites

In a hospital plantroom the window for a changeover may be a single weekend. That only works if everything that can be prepared in advance has been, so that the time on the day goes on the changeover and nothing else.

What to tell your contractor

  • Which systems must stay running, and which can be interrupted.
  • The building's working hours, and when noisy or disruptive work is allowed.
  • The permit system, and who authorises isolations.
  • Access, security and induction arrangements.
  • When each area has to be handed back.

With those five answers a contractor can plan the work around the building, not the other way round.