A building management system (BMS) is the set of controllers, sensors and software that runs a building's heating, cooling, ventilation and energy use. Most large offices, hospitals, hotels and data centres have one.
Two trades usually install it. A controls specialist designs the system, supplies the control panels, writes the software and commissions it. An electrical contractor installs the cabling that connects those panels to the plant. That second part is known as the BMS electrical package, and this guide explains what is normally in it.
Why the electrical side is a separate package
Controls companies specialise in design, software and commissioning. Installing containment and cable across a whole building is a different kind of job: it needs a larger site team with electrical qualifications. So the installation is usually given to an electrical contractor, and the two work side by side until the building is handed over.
1. Containment
Cables need a route before they can be pulled. Containment is the tray, basket, trunking and conduit that carries them through plantrooms, risers and ceiling voids. On a new building the routes are agreed with the other trades first. On a refurbishment they have to fit around what is already there.
2. Power wiring
Control panels need an electrical supply, and so does the equipment they run, such as fans, pumps and fan coil units. The package covers those supplies and the final connection to each item.
3. Controls wiring
This is the wiring between a control panel and the devices around the building: temperature sensors, valves, dampers and meters. Each cable is labelled and numbered to match the drawings, so that anyone opening the panel later can see what goes where.
4. Network wiring
Controllers also talk to each other, and to the building's meters, over data networks. Several types are in common use, including BACnet, Modbus, M-Bus and KNX, along with ordinary Cat6 data cable. Each has its own installation rules, which we cover in a separate guide.
5. Panels and enclosures
Control panels are normally built off site. The electrical contractor takes delivery, moves each panel into position, fixes it in place and connects the incoming cables.
6. Testing and handover
Before the system is switched on, the installation is checked and tested and the results are written down. A package normally ends with test sheets, labelled cables and drawings marked up to show what was actually installed. The electrical team then supports the controls specialist while the system is commissioned.
What is usually not included
The control strategy, the software and the commissioning itself stay with the controls specialist. The mechanical plant and the building's main power distribution are normally separate packages too. It is worth agreeing where each package starts and stops before work begins, so that nothing falls between them.
What a contractor needs to price one
- The scope: which panels, plant and floors are included.
- Drawings and cable schedules, if they exist yet.
- The programme, with any phasing or handover dates.
- Whether the building is occupied, and whether work has to be done out of hours.